Fen Street junction Broughton Grounds Lane – Proposed Resurfacing / Road Closures

Milton Keynes Council is working in partnership with 'Places for People' on the proposed adoption of Fen Street. As part of the remedial works identified by The Council, the developer 'Places for People' have been asked to resurface the full junction of Fen Street / Broughton Grounds Lane. The resurfacing will be carried out in 2 phases during the school summer holidays 2019, in order to minimise inconvenience to local residents and traffic.

Phase 1 - Fen Street /Broughton Grounds Lane, Eastbound.  Carriageway planning, resurfacing and new road markings

  • Dates, 29th July to 31st July 2019 (estimated 2 days’ work, with a 3rd day if required).
  • Road closure will be from 08:00hrs 29th July 2019 and this section of road will remain closed until completion of the works.
  • Fen Street will be open to through traffic, under lane closures and temporary traffic lights.
  • A local signed diversion will be in operation.

Click here to view details of the location and the diversion route (PDF, 262KB)

 

Phase 2– Fen Street / Broughton Grounds Lane, Westbound.  Carriageway planning, resurfacing and new road markings

  • Dates, 31st July to 02nd August 2019 (estimated 2 days’ work with a 3rd day if required).
  • Road closure will be from 08:00hrs 31st July 2019 and this section of road will remain closed until completion of the works.
  • Fen Street will be open to through traffic, under lane closures and temporary traffic lights.
  • A local signed diversion will be in operation.

Click here to view details of the location and the diversion route (PDF, 318KB)

 

Letter to Residents (PDF, 482KB)

The Council apologises, in advance, for any inconvenience caused by these essential road works.

For more information or in case of any issues please email the Project Manager

 

Last Updated: 5 July 2019