Latest news from Highways

For real time information follow us on our social media channels, Facebook (mkcouncil1) and Twitter (@mkcouncil). Our highways service provider Ringway also regularly post updates, news and information on their Twitter account for MK, search for @ringway_mk

Tathall End nr Hanslope bridge works

We'll be carrying out maintenance works on five access bridges in the village of Tathall End starting on 3 August. The work will take around 3 weeks to complete and a road closure will be in place during this time so we can carry out the work safely.

The small bridges allow vehicles to access the properties over the small stream.

Following a structural assessment, it was decided that the old access bridges, which are small concrete slabs, must be removed and replaced with precast concrete ones which will make the installation quicker and easier.

If you have any questions about this or any other structures work please email highwaystructures@milton-keynes.gov.uk or call 01908 252353.

All roadworks, closures and diversion for MK can be viewed at https://one.network/

 

Resurfacing Work - May and June

To find out more about the types of road surfacing we use visit www.mkhighways.co.uk

We'll be carrying out road resurfacing work on sections of the following roads through May and June (weather permitting)

  • High Street, North Crawley                                         
  • St Johns Road, Bletchley                                   
  • Bramber Close, Bletchley                                            
  • Newport Road, Woughton Park (H8 to H9)                                          
  • Clifton road, Newton Blossomville                                     
  • B4034 V8 Marlborough Street H7-H8                                         
  • H3 Monks Way (V9 to V8)                                           
  • Calverton Road (Middle Weald)                                  
  • Tower Drive, Neath Hill                              
  • Newport Road, Broughton                                            
  • Water Eaton Road                                          
  • V11 Tongwell Street (H10)                                       
  • V10 Tilbrook Roundabout                                   
  • V10 Brickhill Street                              
  • A421 H8 Standing Way (V7 to Hospital Roundabout)                                 
  • Princes Way, Bletchley                               
  • Second Avenue, Bletchley                                      
  • Old Wolverton Road. (near Haversham Roundabout)                                  
  • Newport Road, Wavendon                                         
  • Simpson Drive,Simpson                                               
  • Dartmouth road, Olney                            
  • Golden Drive, Eaglestone                                            
  • Colley Hill, Bradwell

 

We'll also be doing some micro-surfacing work on the following sections of grid road too throughout May and June:

  • H9 Groveway (V10 to V11)
  • V8 Marlborough Street (from H7 to H6) Northbound
  • V8 Marlborough Street (from H6 to H7) Southbound
  • V5 Great Monks Street (H1 to H2)
  • H3 Monks Way (V4 to A5)
  • Drayton Road , Bletchley (from Fern Grove to A4146)
  • H8 Standing Way (V6 to V7) eastbound only
  • B4034 V7 Saxon Street (H8 to H9)
  • Newport Road (Woolstone)
  • Pattison Lane (Woolstone)
  • V5 Great Monks Street (A5 to H4)
  • Calverton Road (Upper Weald) Stony Stratford

 

Newport Road, Broughton - traffic calming measures

Work was delayed on this project due to the Covid-19 pandemic but has begun in June and is now complete. More information can be found on the following documents:

Information letter about the scheme (PDF, 98KB)

Plan of the works (PDF, 1.3MB)

 

A421 upgrade  - Eagle Farm roundabout to Junction 13, M1

The A421 between the Eagle Farm Roundabout up to M1 Junction 13 will be closed temporarily overnight on the following dates:

  • Weds 22 July from 8pm until 6am Thurs 23 July
  • Thurs 23 July from 8pm until 6am Fri 24 July
  • Fri 24 July from 8pm until 6am Sat 25 July

 For more information about diversions visit

 www.centralbedfordshire.gov.uk/transport/a421/road-closures.aspx

 

V4 Watling Street

The underpass work site has now reopened following a temporary closure due to the Covid-19 pandemic. We expect the work to be completed and the V4 reopened to vehicles by September 2020.

The Fairfields work site which is being managed by the developer, remained open and work is expected to complete by end July 2020.

Read our Frequently Asked Questions for more information. (PDF, 197KB)

Last Updated: 21 July 2020