Completed Projects and Schemes

 

Signalised junction for V6 Grafton Street/Avebury Boulevard

Started June 2021

Completed November 2021

Aim: to improve capacity and road safety at this location.

View the plans by clicking on the documents below:

Notification of Works - Phase 2 Grafton/Avebury

Traffic Management Plan including diversion routes

 

Tongwell Lane, Newport Pagnell

Started March 2021

Completed August 2021

Aim: to improve the footway to bring it up to redway standard and create a link between Newport Pagnell and the nearby estates to CMK. This scheme was funded by the Active Travel Fund.

 

Brinklow Roundabout, Kingston

Started and completed May 2021

Aim: to improve road safety at this location as the exceptionally cold, wet winter of 20/21 caused existing defects (potholes) to worsen significantly. All the existing road surface was removed and cabling was installed for future use at this location (if needed). 

After the cabling was completed, the roundabout and the approaches were resurfaced with a new layer of asphalt, the linings were repainted and any street lights were repaired. As this is a busy roundabout carrying up to 30,000 vehicles per day, extra highways crews were diverted from other projects. This halved the time it would normally take for a scheme of this scale.

 

Right turn gap closure - V8 Marlborough Street/Peartree Bridge

Started January 2022

Completed April 2022

Aim: to improve road safety at this location following analysis of traffic collision data and a public consultation. The results of the consultation showed the majority of respondents were in favour of the proposals.