Tudor Gardens Redway Link

This project, which began in September 2025, involves creating a safe path for cyclists and pedestrians, resurfacing roads, and installing traffic calming measures like a new raised table and speed humps. The works are expected to last approximately 10 weeks, with some temporary traffic management in place. 

The new redway section will provide a safe route for cyclists and pedestrians between Fairfields and Stony Stratford. The link will go through Tudor Gardens and Calverton End, connecting with the existing redway network.

A public consultation took place in January-February 2024. You can view the results report here.

Construction phases:

  • Work began in September 2025 and is expected to last about 10 weeks, weather permitting.
  • The project includes resurfacing, the construction of a new redway, and traffic calming measures.
  • Measures are being taken to protect the environment, including supervision by an ecologist and the installation of bat boxes.

    Traffic calming:

  • In addition to the new redway, traffic calming features will be installed, including a 20mph speed limit, speed humps, and a new crossing.
  • These measures are intended to improve safety along the H1 Ridgeway in this area. 

To view the plans for the construction, click on the documents below:

Tudor Gardens Plan

Ecology Study

You can view the letters to residents below:

Letter 1 - August 

Letter 2 - October

Letter 3 - October